Baseline schedule
Contents |
[edit] Introduction
Time management is one of the most important processes in project management. It is the discipline of planning and controlling the duration of a project. A baseline schedule is one of the main project management documents that should be created before the project starts. It sets out the project execution strategy, key project deliverables, activity planned dates and milestones.
Activities are grouped under different work breakdown structure levels. Engineering, procurement, production, testing, and so on are highlighted in baseline schedules.
[edit] Baseline schedule
A baseline schedule (also known as a schedule baseline or target schedule) is an approved copy of the project schedule that can be used to analyse project performance and report schedule variances. Baseline schedules create a road map to prepare the baseline budget, mobilisation plans, and resource allocation plans.
According to the Project Management Body of Knowledge (PMBOK) Guide, a Project Schedule represents 'the planned dates for performing activities and the planned dates for meeting milestones.'
Baselines are the frozen version of the project schedules. Before updating the project schedule for the first time, the baseline schedule is retained as a target. This means the baseline schedule is the same as the project schedule at the beginning.
As the project progresses and tasks are performed, the baseline schedule may deviate from the actual schedule. It may not reflect the current project status. Risks and unforeseen events may affect it, and some changes outside of the control of the project management team may cause delays.
Under these circumstances, remedial action should be taken and recovery plans created. It is important to emphasise that baselines should only be changed when there is a change in scope.
[edit] Baseline schedule tracking
After the approval of the baseline schedule by the stakeholders, it will be retained as a target. Schedule tracking is then carried out to analyse the differences between the planned and the actual dates. Changes in the critical path, schedule variances and delays are determined and reported in all updates.
[edit] Summary
In project time management, baseline schedules are used as references to analyse the schedule performance of the project. It is a reference document which compares the planned and the actual dates. A Schedule Performance Index (SPI) can be used to understand how far ahead or behind the project is at the point of analysis.
See also: Baseline programme.
[edit] Related articles on Designing Buildings Wiki
- Activity schedule.
- Contractor's master programme.
- Contractor's working schedule.
- Design programme.
- How progress is agreed in construction.
- Milestones.
- Programme for building design and construction.
- Scheduling construction activities.
- Time management of construction projects.
[edit] External resources
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.